Referenciák | References
|
ENCO ENGINEERING LTD. REFERENCE LIST 2003-2015 |
||||
PHARMACEUTICAL AND MEDICAL DEVICE FACTORY PROJECTS |
SITE |
TYPE OF DESIGN |
CUSTOMER |
YEAR |
|
COLOPLAST VII. HVAC AND MECH.SYSTEMS, CLEAN AREAS |
TATABÁNYA/HUNGARY |
UNDER DESIGN |
COLOPLAST/DENMARK |
2016 |
|
RICHTER GEDEON DOROG, NEW CHILLER ROOM |
DOROG, HUNGARY |
FINAL DESIGN |
GEDEON RICHTER PHARMACEUTICAL COMPANY |
2015 |
|
COLOPLAST V PHASE: HVAC SYSTEM, CLEAN AREAS |
NYÍRBÁTOR, HUNGARY |
FINAL DESIGN |
COLOPLAST/DENMARK |
2014 |
|
GLAXOSMITHKLINE BIOLOGICALS: NEW CHILLERS INSTALLATION CAP:4.2 MW |
GÖDÖLLŐ, HUNGARY |
FINAL DESIGN |
GLAXOSMITHKLINE BIOLOGICALS/BELGIUM |
2014-2015 |
|
RICHTER GEDEON RGK VI. PROJECT. BASIC DESIGH, HEATING, COOLING AND STEAM SYSTEMS |
BUDAPEST, HUNGARY |
BASIC DESIGN |
GEDEON RICHTER PHARMACEUTICAL COMPANY |
2014 |
|
RICHTER GEDEON NEW CHILLER ROOM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
GEDEON RICHTER PHARMACEUTICAL COMPANY |
2014 |
|
EGIS API-K PROJECT MECHANICALSYSTEMS, |
BUDAPEST, HUNGARY |
FINAL DESIGN |
EGIS/SERVIER, HUNGARY |
2013-2015 |
|
GLAXOSMITHKLINE BIOLOGICALS EXTENSION, HVAC SYSTEMS |
GÖDÖLLŐ, HUNGARY |
FINAL DESIGN |
GLAXOSMITHKLINE BIOLOGICALS/BELGIUM |
2014-2015 |
|
GLAXOSMITHKLINE BIOLOGICALS: HEAT PUMP SYSTEM RETROFIT, |
GÖDÖLLŐ, HUNGARY |
FINAL DESIGN |
GLAXOSMITHKLINE BIOLOGICALS /BELGIUM |
2011-2012 |
|
RICHTER GEDEON DBP PROJECT. CHILLER AND BOILER PLANT EXTENSION, |
DEBRECEN, HUNGARY |
FINAL DESIGN |
GEDEON RICHTER PHARMACEUTICAL COMPANY |
2011-2012 |
|
COLOPLAST : HVAC SYSTEM, MUNTERS DRYERS, |
NYÍRBÁTOR, HUNGARY |
FINAL DESIGN |
COLOPLAST/DENMARK |
2011 |
|
GSC PROJECT:CHILLED WATER PLANT CAP:7,5 MW |
GÖDÖLLŐ, HUNGARY |
FINAL DESIGN |
TEVA PHARMACEUTICAL COMPANY |
2011 |
|
RESEARCH CENTRE FOR NATURAL SCIENCES OF THE HUNGARIAN ACADEMY OF SCIENCES: HVAC & MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
HUNGARIAN ACADEMY OF SCIENCES |
2011- |
|
GSC PROJECT:UTILITIES, PROCESS PIPING SYSTEMS |
GÖDÖLLŐ, HUNGARY |
FINAL DESIGN |
TEVA PHARMACEUTICAL COMPANY /COOPTECH |
2010-2011 |
|
HUMAN BIOPLAZMA MECHANICAL SYSTEMS, PRODUCTION BUILDING:UTILITIES MECHANICAL AND HVAC SYSTEMS |
GÖDÖLLŐ, HUNGARY |
FINAL DESIGN |
FOSTER WHEELER ITALY/COOPTECH |
2010 |
|
EGIS KÖRMEND REFRIGERATION SYSTEM RETROFIT PRODUCTION BUILDING:UTILITIES MECHANICAL AND HVAC SYSTEMS |
KÖRMEND, HUNGARY |
FINAL DESIGN |
EGIS PHARMACEUTICAL COMPANY |
2010 |
|
RICHTER GEDEON DBP PROJECT, DEBRECEN, PRODUCTION BUILDING:UTILITIES MECHANICAL AND HVAC SYSTEMS |
DEBRECEN, HUNGARY |
FINAL DESIGN |
GEDEON RICHTER PHARMACEUTICAL COMPANY |
2009-2011 |
|
AMRI LABS, GRAPHISOFT IND. PARK: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
ALBANY/NY/USA, |
2008-2009 |
|
COLOPLAST PHASE 4TH : MECHANICAL SYSTEM |
NYÍRBÁTOR, HUNGARY |
FINAL DESIGN |
COLOPLAST/DENMARK |
2007 |
|
SERVIER LABORATORY: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
SERVIER/TESCHIP/FRANCE |
2006 |
|
COLOPLAST 3RD PHASE HVAC AND MECH. SYSTEMS, C |
TATABÁNYA/HUNGARY |
FINAL DESIGN |
COLOPLAST/DENMARK |
2003-2004 |
|
COLOPLAST 3RD PHASE HVAC AND MECH. SYSTEMS, CLEAN AREAS |
TATABÁNYA/HUNGARY |
FINAL DESIGN |
COLOPLAST/DENMARK |
2003-2004 |
OFFICE BUILDINGS AND OTHER PROJECTS |
SITE |
TYPE OF DESIGN |
CUSTOMER |
YEAR |
|
GRAPHISOFT START UP BUILDING |
BUDAPEST, HUNGARY |
UNDER DESIGN |
GRAPHISOFT LTD |
2016 |
|
GRAPHISOFT SAP BUILDINGS RECONSTRUCTION |
BUDAPEST, HUNGARY |
UNDER DESIGN |
GRAPHISOFT LTD |
2015-2016 |
|
‘KONKOLY’ OBSERVATORY OF THE HUNGARIAN ACADEMY OF SCIENCES |
BUDAPEST, HUNGARY |
UNDER DESIGN |
HUNGARIAN ACADEMY OF SCIENCES (NATIONAL PROJECT) |
2015-2016 |
|
GRAPHISOFT NEW SAP BUILDING |
BUDAPEST, HUNGARY |
FINAL DESIGN |
GRAPHISOFT LTD |
2015-2016 |
|
VVSI AGÁRD REHABILITATION CENTER COMPLETE HVAC SYSTEM |
AGÁRD, HUNGARY |
FINAL DESIGN |
KIMA STUDIO (NATIONAL PROJECT)/HUNGARY |
2014 |
|
FEASIBILITY STUDY OF PERMANENT FIRE PROOF TENTS FOR ARAFAT AREA |
SAUDI, ARAFAT AREA |
STUDY |
SAUDI ARABIA, STUDIO IN-EX ARCH. LTD |
2013 |
|
HIGHWAY TUNNELS DESIGN CHECKING |
KURDISTAN, IRAQ |
CONSULTATION |
KURDISTAN REGIONAL GOVERMENT |
2013 |
|
GRUNDFOS MANUFACTURING PLANT: MECHANICAL SYSTEM – 2ND PHASE |
SZÉKESFEHÉRVÁR, HUNGARY |
FINAL DESIGN |
GRUNDFOS |
2013 |
|
GRUNDFOS SZÉKESFEHÉRVÁR: GMHIV, NEW FACTORY HVAC & MECHANICAL SYSTEMS |
SZÉKESFEHÉRVÁR, HUNGARY |
FINAL DESIGN |
STRABAG |
2012-2013 |
|
OFFICE BUILDING CORVIN113/A-2: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
FUTUREAL |
2010-2012 |
|
BANK CENTER : HVAC & MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
TOP TORONY LTD. |
2012-2013 |
|
GRAPHISOFT NO57 BUILDING MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
GRAPHISOFT LTD |
2011-2012 |
|
ESZTERGOMI KANONOKSOR HIGHSCHOOL: MECHANICAL SYSTEM |
ESZTERGOM, HUNGARY |
FINAL DESIGN |
ESZTRG.ÖNKOR. |
2009 |
|
BUDAPEST AIRPORT RECONSTRUCTION: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
L.F. INTERNATIONAL AIRPORT |
2009 |
|
PREFABRICATED CONCRETE-MANUFACTURING PLAN; MECH. SYS |
UKRAINE |
TENDER |
KÉSZ LTD |
2008 |
|
GRAPHISOFT OFFICE BUILDING MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
GRAPHISOFT LTD |
2008 |
|
TESCO STORE: MECHANICAL SYSTEM WITH HEAT PUMP |
DUNAKESZI, HUNGARY |
FINAL DESIGN |
TESCO GLOBAL |
2007 |
|
OFFICE BUILDING CORVIN113/A-2: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
FUTUREAL |
2010-2012 |
|
EXEDY MANUFACTURING PLANT: MECHANICAL SYSTEM |
TATABÁNYA, HUNGARY |
FINAL DESIGN |
EXEDY/JAPAN |
2007 |
|
IP WEST OFFICE BUILDING 2ND PHASE: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
AIG/LINCOLN |
2007 |
|
OFFICE BUILDING CORVIN113/A: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
FUTUREAL |
2007 |
|
SAP OFFICE BUILDING, GRAPHISOFT IND. PARK: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
GRAPHISOFT LTD |
2007 |
|
TESCO GLOBAL 3K: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
TESCO GLOBAL |
2007 |
|
LEMO SA MANUFACTURING PLANT: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
TENDER DESIGN |
LEMO SA/SWITZERLAND |
2007 |
|
TESCO STORE 3K: MECHANICAL SYSTEM |
BBOGLÁR, HUNGARY |
FINAL DESIGN |
TESCO GLOBAL |
2007 |
|
JABIL MANUFACTURING PLANT : MECHANICAL SYSTEM |
KWIDZYN/POLAND |
FINAL DESIGN |
KÉSZ LTD |
2007 |
|
GLAXO SMITH KLINE OFFICE BUILDING: MECHANICAL SYSTEM |
GÖDÖLŐ, HUNGARY |
FINAL DESIGN |
GLAXO SK. |
2007 |
|
TESCO WAREHOUSE 2ND PHASE:MECHANICAL SYSTEM |
GYÁL, HUNGARY |
FINAL DESIGN |
TESCO GLOBAL |
2007 |
|
TESCO STORE 5K: MECHANICAL SYSTEM |
HATVAN, HUNGARY |
FINAL DESIGN |
TESCO GLOBAL |
2007 |
|
HOLCIM CEMENT PRODUCTION |
LÁBATLAN, HUNGARY |
FINAL DESIGN |
KÉSZ LTD |
2006 |
|
SANYO MANUFACTURING PLANT PHASE 5: MECHANICAL SYSTEM |
DOROG, HUNGARY |
FINAL DESIGN |
TAKENAKA/JAPAN |
2006 |
|
GRUNDFOS MANUFACTURING PLANT: MECHANICAL SYSTEM – 1ST PHASE |
SZ FEHÉRVÁR, HUNGARY |
FINAL DESIGN |
GRUNDFOS |
2006 |
|
JABIL MANUFACTURING PLANT: MECHANICAL SYSTEM |
UNGVÁR /UKRAINE |
FINAL DESIGN |
KÉSZ LTD |
2006 |
|
OFFICE BUILDING CORVIN113/B: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
FUTUREAL |
2006 |
|
SPORT ARENA KISKUNFÉLEGYHÁZA: MECHANICAL SYSTEM |
KKUNFÉLEGYHÁZA, H. |
FINAL DESIGN |
KÉSZ LTD |
2006 |
|
TESCO STORE: MECHANICAL SYSTEM |
HSZOBOSZLÓ, HUNGARY |
FINAL DESIGN |
TESCO GLOBAL |
2006 |
|
PANNON OFFICE BUILDING: MECHANICAL SYSTEM AND HEAT PUMPS |
TÖRÖKBALINT, HUNGARY |
FINAL DESIGN |
PANNON GSM |
2006 |
|
TESCO STORE: MECHANICAL SYSTEM WITH HEAT PUMP |
DOROG, HUNGARY |
FINAL DESIGN |
TESCO GLOBAL |
2006 |
|
TESCO STORE: MECHANICAL SYSTEM |
KKUNLACHÁZA, HUNGARY |
FINAL DESIGN |
TESCO GLOBAL |
2006 |
|
TESCO ARENA PLAZA SHOPPING CENTER: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
TESCO GLOBAL |
2006 |
|
T-ONLINE AXELERO CENTER:IT ROOM HVAC SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
T-ONLINE |
2006 |
|
GRUNDFOS TATABÁNYA: COOLING SYSTEM |
TATBÁNYA, HUNGARY |
FINAL DESIGN |
GRUNDFOS HUNGARY |
2006 |
|
MAKITA MANUFACTURING PLANT: MECHANICAL SYSTEM |
ROMÁNIA |
FINAL DESIGN |
TAKENAKA/JAPAN |
2005 |
|
SHOPPING CENTER KOLOZSVÁR: MECHANICAL SYSTEM |
KOLOZSVÁR, ROMÁNIA |
FINAL DESIGN |
ARCADOM LTD |
2005 |
|
DECATLON ÁRUHÁZ, CSÖMÖR: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
TENDER DESIGN |
DECATLON |
2005 |
|
SAP OFFICE BUILDING, GRAPHISOFT IND. PARK: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
GRAPHISOFT LTD |
2005 |
|
BSR OFFICE BUILDING: MECHANICAL SYSTEM |
BUDAPEST, HUNGARY |
FINAL DESIGN |
BSR GROUP |
2005 |
|
POLUS SHOPPING CENTER KOLOZSVAR HVAC SYSTEMS |
KOLOZSVÁR ROMANIA |
TENDER DESIGN |
ARCADOM LTD |
2005 |
|
JABIL CIRCUIT SERVICE PLANT: MECHANICAL SYSTEMS |
SZOMBATHELY/HUNGARY |
FINAL DESIGN |
JABIL/USA/FLORIDA |
2005 |
|
JABIL CIRCUIT MICROELECTRONIC PLANT: MECHANICAL SYSTEMS |
UNGVAR/UKRAINE |
TENDER DESIGN |
JABIL/USA/FLORIDA |
2005 |
|
AXELERO: CLOSE CONTROL SYSTEM FOR COMPUTER ROOM |
BUDAPEST/HUNGARY |
FINAL DESIGN |
MATÁV RT |
2004 |